Preventive Maintenance for the Injection Unit

Most injection unit failures announce themselves weeks in advance. A schedule that catches them is cheaper than any spare part.
Daily
- Check cushion stability and record it; a drifting cushion is the earliest wear signal
- Look for resin drool around the nozzle and heater bands
- Confirm all zones reach setpoint within the normal time
- Listen for unusual noise from the injection unit during recovery
Monthly
- Measure heater resistance and insulation to earth on each zone
- Check terminal screws for tightness and discoloration
- Inspect nozzle tip and seat for wear and damage
- Verify barrel support and alignment; check for movement at the feed throat
- Review shot weight records for drift
Annually, or on major service
- Pull the screw and measure flight OD and barrel bore at three positions
- Inspect the check ring and seat; replace as a set if worn
- Inspect the screw for cracks at the flight root and at the drive end
- Replace heater bands showing more than 10% resistance drift
- Check barrel straightness and the condition of the feed throat liner
Record keeping that actually helps
A single measurement tells you little. A trend tells you when to order parts. Keep a one-page log per machine: date, cushion, recovery time, shot weight, heater resistances, and any work done. When the trend bends, you have weeks of warning instead of a breakdown on a Friday afternoon.